Contents
Executive Summary
1.1 Purpose of the Report
1.2 Structure of the Report
2.1 Background
2.2 General Site Description
2.3 Major Activities Undertaken
2.4 Project Organisation and Management Structure
2.5 Status of Environmental Approval Documents
3 Environmental Monitoring and Audit Requirements
3.1 Environmental Monitoring
3.1.1 Air Quality
3.1.2 Odour
3.2 Site Audit
3.2.1 Water Quality
3.2.2 Landscape and Visual
4.1 Air Quality
4.1.1 Commissioning Phase Monitoring
4.1.2 Operation Phase Monitoring
4.2 Odour
4.2.1 Operation Phase Monitoring
4.3 Water Quality
4.3.1 Operation Phase Monitoring
4.4 Waste Management
4.4.1 Operation Phase Monitoring
5.1 Environmental Site Audit
5.1.1 Operation Phase
5.2 Landscape and Visual Audit
6 Environmental Non-conformance and Deficiencies
6.1 Summary of Environmental Non-Compliance and Deficiencies
6.2 Summary of Environmental Complaint
6.3 Summary of Environmental Summon and Successful Prosecution
7.1 Key Issues for the Coming Month
LIST OF TABLES
Table 2.1 Summary of Activities Undertaken in the Reporting Period
Table 2.2 Summary of Environmental Licensing, Notification and Permit Status
Table 3.1Sampling and Laboratory Analysis Methodology
Table 3.2Emission Limit for CAPCS Stack
Table 3.3Emission Limit for CHP Stack
Table 3.4Emission Limit for ASP Stack
Table 3.5Emission Limit for Standby Flaring Gas Unit ()
Table 3.6Odour Intensity Level
Table 3.7Action and Limit Levels for Odour Nuisance
Table 3.8Event and Action Plan for Odour Monitoring
Table 3.9Discharge Limits for Effluent
Table 4.1 Hourly Average of Parameters Recorded for CAPCS
Table 4.2 Hourly Average of Parameters Recorded for CHP 1
Table 4.3 Hourly Average of Parameters Recorded for CHP 2
Table 4.4 Hourly Average of Parameters Recorded for CHP 3
Table 4.5Hourly Average of Parameters Recorded for ASP
Table 4.6Results of the Discharge Sample
Table 4.7Quantities of Waste Generated from the Construction of the Project
Table 4.8 Quantities of Waste Generated from the Operation of the Project
LIST OF ANNEXES
Annex A |
|
Annex B |
|
Annex C |
Calibration Certification for the On-line Stack Monitoring System |
Annex D |
|
Annex E |
|
Annex F |
Environmental complaint, Environmental Summons and Prosecution Log |
Annex G |
EXECUTIVE SUMMARY
The construction works of No. EP/SP/61/10 Organic Resources Recovery Centre Phase 1 (the Project) commenced on 21 May 2015. This is the 59th monthly Environmental Monitoring and Audit (EM&A) report presenting the EM&A works carried out during the period from 1 to 30 April 2020 in accordance with the EM&A Manual. Substantial completion of the construction works was confirmed on 3 December 2018. In the meantime, the operation phase EM&A programme had commenced in March 2019. Substantial Completion in respect of substantial part of the Works was confirmed on 24 February 2020. The construction phase EM&A programme was completed in the end of February 2020.
Summary of Works undertaken during the Reporting Month
Works undertaken in the reporting month included:
· Operation of the Project, including organic waste reception, and operation of the pre-treatment facilities, anaerobic digesters, composting facilities, air pollution control systems, on-line emission monitoring system for the Centralised Air Pollution Control Unit (CAPCS), Co-generation Units (CHP)s and Ammonia Stripping Plant (ASP), and the wastewater treatment plant; and
· Process fine-tune, including adjustment of the ASP with new treatment media, modification of Continuous Environmental Monitoring System (CEMS) and Supervisory Control and Data Acquisition System (SCADA) rectification and improvement works following equipment failures and the alteration of different operation modes and measures to adapt to the high variation of SSOW nature and sources.
Environmental Monitoring and Audit Progress
Air Quality Monitoring
Exceedances on Odour (including NH3 & H2S) from CAPCS, NOx, and VOCs (including methane) from CHP and Carbon Monoxide, NOx, VOCs (including methane), NH3 and HF from ASP were recorded on the on-line monitoring system. It should be noted that measurements recorded under abnormal operating conditions, e.g. start up and stopping of stacks, unstable operation, test runs and interference of sensor, are disregarded.
Exceedances in emission parameters of CAPCS, CHP and ASP were found to be a result of problems with the continuous fine-tuning of CAPCS and CHP settings, and the incomplete thermal combustion of the thermal combustion unit of the ASP.
The Contractor has implemented mitigation measures to control the exceedance (including the re-adjustment of CAPCS and CHP; and tuning the thermal combustion unit of the ASP to optimise combustion efficiency and overall performance).
The Contractor is recommended to closely monitor the processes of the modification of the ASP and the post-modification monitoring of emission level to avoid any exceedance.
No non-compliance to the effluent discharge limit stipulated in the discharge licence issued by the EPD under the Water Pollution Control Ordinance was recorded during this reporting period.
Waste generated from the operation of the Project includes chemical waste, waste generated from pre-treatment process and general refuse.
0 L of chemical waste was collected by licenced waste collector from the operation of the Project.
363.92 tonnes of waste generated from pre-treatment process from the operation of the Project was disposed of at landfill. Among the recyclable waste generated from pre-treatment process from the operation of the Project, 0.00 kg of metals, 0.00 kg of papers/ cardboard packing and 0.00 kg of plastics were sent to recyclers for recycling during the reporting period.
Around 2.42 tonnes of general refuse from the operation of the Project was disposed of at landfill. Among the recycled general refuse from the operation of the Project, 0.00 kg of metals, 0.00 kg of papers/ cardboard packing and 0.00 kg of plastics were sent to recyclers for recycling during the reporting period.
Findings of Environmental Site Audit
A summary of the monitoring activities undertaken in this reporting period is listed below:
· Joint Environmental Site Inspections |
1 time |
1 monthly joint environmental site inspections were carried out by the representatives of the Contractor and the ET. The ER and IEC were also present at the joint inspections on 23 April 2020. The environmental control/ mitigation measures (related to air quality, water quality, waste (including land contamination prevention), hazard-to-life and landscape and visual) recommended in the approved EIA Report and the EM&A Manual were properly implemented by the Contractor during the reporting month.
Environmental Exceedance/Non-conformance/Compliant/Summons and Prosecution
Exceedances for the air emission limits for the CAPCS, CHP and ASP stacks were recorded during the reporting period.
No complaint/ summon/prosecution was received in this reporting period.
Future Key Issues
Activities to be undertaken in the next reporting month include:
· Operation of the Project.
· Modification of the ASP to control the air emission.
ERM-Hong Kong, Limited (ERM) was appointed by OSCAR Bioenergy Joint Venture (the Contractor) as the Environmental Team (ET) to undertake the construction Environmental Monitoring and Audit (EM&A) programme for the Contract No. EP/SP/61/10 of Organic Waste Treatment Facilities Phase I, which the project name has been updated to Organic Resources Recovery Centre (Phase I) (the Project) since November 2017. ERM was also appointed by the Contractor to undertake the operation EM&A programme starting 1 March 2019.
This is the 59th EM&A report which summarises the monitoring results and audit findings for the EM&A programme during the reporting period from 1 to 30 April 2020.
The structure of the report is as follows:
Section 1: Introduction
It details the scope and structure of the report.
Section 2: Project Information
It summarises the background and scope of the Project, site description, project organisation and status of the Environmental Permits (EP)/licences.
Section 3: Environmental Monitoring and Audit Requirements
It summarises the environmental monitoring requirements including monitoring parameters, programmes, methodologies, frequency, locations, Action and Limit Levels, Event/Action Plans, as well as environmental audit requirements as recommended in the EM&A Manual and approved EIA report.
Section 4: Monitoring Results
It summarises monitoring results of the reporting period.
Section 5: Site Audit
It summarises the audit findings of the environmental as well as landscape and visual site audits undertaken within the reporting period.
Section 6: Environmental Non-conformance
It summarises any exceedance of environmental performance standard, environmental complaints and summons received within the reporting period.
Section 7: Further Key Issues
It summarises the impact forecast for the next reporting month.
Section 8: Conclusions
The Organic Resources Recovery Centre (ORRC) Phase I development (hereinafter referred to as “the Project”) is to design, construct and operate a biological treatment facility with a capacity of about 200 tonnes per day and convert source-separated organic waste from commercial and industrial sectors (mostly food waste) into compost and biogas through proven biological treatment technologies. The location of the Project site is shown in Annex A.
The environmental acceptability of the construction and operation of the Project had been confirmed by findings of the associated Environmental Impact Assessment (EIA) Study completed in 2009. The Director of Environmental Protection (DEP) approved this EIA Report under the Environmental Impact Assessment Ordinance (EIAO) (Cap. 499) in February 2010 (Register No.: AEIAR-149/2010) (hereafter referred to as the approved EIA Report). Subsequent Report on Re-assessment on Environmental Implications and Report on Re-assessment on Hazard to Life Implications were completed in 2013, respectively.
An Environmental Permit (EP) (No. EP-395/2010) was issued by the DEP to the EPD (Project Team), the Permit Holder, on 21 June 2010 and varied on 18 March 2013 (No. EP-395/2010/A) and 21 May 2013 (No. EP-395/2010/B), respectively. The Design Build and Operate Contract for the ORRC Phase 1 (Contract No. EP/SP/61/10 Organic Resources Recovery Centre (Phase 1) (the Contract)) was awarded to SITA Waste Services Limited, ATAL Engineering Limited and Ros-Roca, Sociedad Anonima jointly trading as the OSCAR Bioenergy Joint Venture (OSCAR or the Contractor). A Further EP (No. FEP-01/395/2010/B) was issued by the DEP to the OSCAR on 16 February 2015. Variation to both EPs (Nos. EP-395/2010/B and FEP-01/395/2010/B) were made in December 2015. The latest EPs, Nos. EP-395/2010/C and FEP-01/395/2010/C, were issued by the DEP on 21 December 2015.
Under the requirements of Condition 5 of the EP (No. FEP-01/395/2010/C), an Environmental Monitoring and Audit (EM&A) programme as set out in the approved EM&A Manual (hereinafter referred to as EM&A Manual) is required to be implemented during the construction and operation of the Project. ERM-Hong Kong, Ltd (ERM) has been appointed by OSCAR as the Environmental Team (ET) for the construction phase EM&A programme and the Monitoring Team (MT) for the operation phase EM&A programme for the implementation of the EM&A programme in accordance with the requirements of the EP and the approved EM&A Manual.
The construction works commenced on 21 May 2015. The operation phase of the EM&A programme commenced on 1 March 2019 ([1]). The construction phase EM&A programme was completed in the end of February 2020.
The Project Site is located at Siu Ho Wan in North Lantau with an area of about 2 hectares. The layout of the Project Site is illustrated in Annex A. The facility received and treated an average of 100 tonnes of source separated organic waste per day during the reporting month.
A summary of the major activities undertaken in the reporting period is shown in Table 2.1.
Table 2.1 Summary of Activities Undertaken in the Reporting Period
Activities Undertaken in the Reporting Period |
· Systems being operated – waste reception, pre-treatment, CAPCS extraction, the digesters, the centrifuge, , the composting tunnels the desulphurisation, the emergency flare, the CHPs, the ASP and the biological waste water treatment plant (about 100-130 t/d SSOW input); and · Process fine-tune – adjustment of the ASP operational parameters with new treatment media, CEMS/SCADA modification and improvement work following equipment failures and the alteration of different operation modes and measures to adapt to the high variation of SSOW nature and sources. |
The project organisation chart and contact details are shown in Annex B.
A summary of the valid permits, licences, and/or notifications on environmental protection for this Project is presented in Table 2.2.
Table 2.2 Summary of Environmental Licensing, Notification and Permit Status
Permit/ Licences/ Notification |
Reference |
Validity Period |
Remarks |
Environmental Permit |
FEP-01/395/2010/C
|
Throughout the Contract
|
Permit granted on 21 December 2015
|
Effluent Discharge License |
WT00024352-2016 |
3 June 2016 – 30 June 2021 |
Approved on 3 June 2016 |
Chemical Waste Producer Registration |
WPN 5213-961-O2231-02 |
Throughout the implementation of the Project |
Approved on 10 November 2017 |
Waste Disposal Billing Account |
Account number: 702310 |
Throughout the Contract |
- |
The air quality (including odour) monitoring to be carried out during the commissioning and operation phase of the Project are described below. Although water quality monitoring is not required for the operation phase under the EM&A programme, there are water quality monitoring requirement under the Water Discharge Licence of the plant under the Water Pollution Control Ordinance (WPCO). As part of this EM&A programme, the monitoring results will be reviewed to check the compliance with the WPCO requirements.
According to the EM&A Manual and EP requirements, stack monitoring are required during the commissioning and operation phase of the Project.
On-line monitoring (using continuous environmental monitoring system (CEMS) shall be carried out for the centralised air pollution unit (CAPCS), cogeneration units (CHP) and the ammonia stripping plant (ASP) during the commissioning and operation phase. The calibration certificate for the on-line monitoring equipment is provided in Annex C.
The monitoring data is transmitted instantaneously to EPD (Regional Office) by telemetry system.
When the on-line monitoring for certain parameter cannot be undertaken, monitoring will be carried out using the following methodology approved by the EPD.
Table 3.1 Sampling and Laboratory Analysis Methodology
Parameters |
Method |
Stacks to be Monitored |
Gaseous and vaporous organic substances (including methane) |
USEPA Method 18 |
· CAPCS · CHP · ASP |
Particulate |
USEPA Method 5 |
· CAPCS · CHP · ASP |
Carbon monoxide (CO) |
USEPA Method 10 |
· CHP · ASP |
Nitrogen oxides (NOx) |
USEPA Method 7E |
· CHP · ASP |
Sulphur dioxide (SO2); |
USEPA Method 6 |
· CHP · ASP |
Hydrogen chloride (HCl) |
USEPA Method 26A |
· CHP · ASP |
Hydrogen fluoride (HF) |
USEPA Method 26A |
· CHP · ASP |
Oxygen (O2); |
USEPA Method 3A |
· CAPCS · CHP · ASP |
Velocity and Volumetric Flow |
USEPA Method 2 |
· CAPCS · CHP · ASP |
Ammonia (NH3) |
USEPA CTM 027 |
· ASP |
Odour (including NH3 and H2S) |
EN 13725 |
· CAPCS |
Water vapour content (continuous measurement of the water vapour content should not be required if the sample exhaust gas is dried before the emissions are analysed) |
USEPA Method 4 |
· CAPCS · CHP · ASP |
Temperature |
USEPA Method 4 |
· CAPCS · CHP · ASP |
With reference to the EM&A Manual, the air emission of the stacks shall meet the following emission limits as presented in Tables 3.2 to 3.5.
Table 3.2 Emission Limit for CAPCS Stack
Parameter |
Emission Level (mg/Nm3) (a) |
VOCs (including methane) |
680 |
Dust (or Total Suspended Particulates (TSP)) |
6 |
Odour (including NH3 & H2S) |
220 (b) |
Notes: (a) Hourly average concentration (b) The odour unit is OU/Nm3 |
Table 3.3 Emission Limit for CHP Stack
Parameter |
Maximum Emission Level (mg/Nm3) (a) (b) |
Dust (or Total Suspended Particulates) |
15 |
Carbon Monoxide |
650 |
NOx |
300 |
SO2 |
50 |
NMVOCs (c) |
150 |
VOCs (including methane) (d) |
1,500 |
HCl |
10 |
HF |
1 |
Notes: (a) All values refer to an oxygen content in the exhaust gas of 6% and dry basis. (b) Hourly average concentration (c) NMVOCs should be monitored by gas sampling and laboratory analysis at an agreed interval. For the first 12 months (starting from August 2019), monitoring should be carried out at quarterly intervals. The monitoring frequency should then be reduced to half-yearly for next 12 months (starting from August 2020). (d) The VOCs emission limit include methane as biogas is adopted as fuel in the combustion process. |
Table 3.4 Emission Limit for ASP Stack
Parameter |
Maximum Emission Level (mg/Nm3) (a) (b) |
Dust (or Total Suspended Particulates) |
5 |
Carbon Monoxide |
100 |
NOx |
200 |
SO2 |
50 |
VOCs (including methane) (c) |
20 |
NH3 |
35 |
HCl |
10 |
HF |
1 |
Notes: (a) All values refer to an oxygen content in the exhaust gas of 11% and dry basis. (b) Hourly average concentration (c) The VOCs emission limit include methane as biogas is adopted as fuel in the combustion process. |
Table 3.5 Emission Limit for Standby Flaring Gas Unit ([2])
Parameter |
Maximum Emission level (mg/Nm3) (a) (b) |
Dust (or Total Suspended Particulates) |
5 |
Carbon Monoxide |
100 |
NOx |
200 |
SO2 |
50 |
VOCs (including methane) (c) |
20 |
HCl |
10 |
HF |
1 |
Notes: (a) All values refer to an oxygen content in the exhaust gas of 11% and dry basis. (b) Hourly average concentration (c) The VOCs emission limit include methane as biogas is adopted as fuel in the combustion process. |
To determine the effectiveness of the proposed odour mitigation measures and to ensure that the operation of the ORRC1 will not cause adverse odour impacts, odour monitoring of the CAPCS stack (see Section 3.1.1) and odour patrol will be carried out.
Odour patrol shall be conducted by independent trained personnel/ competent persons in summer months (i.e. from July to September) for the first two operational years of ORRC1 at monthly intervals along an odour patrol route at the Project Site boundary as shown in Annex A([3]).
The perceived odour intensity is divided into 5 levels. Table 3.6 describes the odour intensity for different levels.
Table 3.6 Odour Intensity Level
Level |
Odour Intensity |
0 |
Not detected. No odour perceived or an odour so weak that it cannot be easily characterised or described |
1 |
Slight identifiable odour, and slight chance to have odour nuisance |
2 |
Moderate identifiable odour, and moderate chance to have odour nuisance |
3 |
Strong identifiable, likely to have odour nuisance |
4 |
Extreme severe odour, and unacceptable odour level |
Table 3.7 shows the action level and limit level to be used for odour patrol. Should any exceedance of the action and limit levels occurs, actions in accordance with the event and action plan in Table 3.8 should be carried out.
Table 3.7 Action and Limit Levels for Odour Nuisance
Parameter |
Action Level |
Limit Level |
Odour Nuisance (from odour patrol) |
When one documented compliant is received (a), or Odour Intensity of 2 is measured from odour patrol. |
Two or more documented complaints are received (a) within a week; or Odour intensity of 3 or above is measured from odour patrol. |
Note: (a) Once the complaint is received by the Project Proponent (EPD), the Project Proponent would investigate and verify the complaint whether it is related to the potential odour emission from the ORRC1 and its on-site wastewater treatment unit. |
Table 3.8 Event and Action Plan for Odour Monitoring
Event |
Action |
|
|
Person-in-charge of Odour Monitoring |
Project Proponent (a) |
Action Level |
|
|
Exceedance of action level (Odour Patrol) |
1. Identify source/reason of exceedance; 2. Repeat odour patrol to confirm finding. |
1. Carry out investigation to identify the source/reason of exceedance. Investigation should be completed within 2 weeks; 2. Rectify any unacceptable practice; 3. Implement more mitigation measures if necessary; 4. Inform Drainage Services Department (DSD) or the operator of the Siu Ho Wan Sewage Treatment Works (SHWSTW) if exceedance is considered to be caused by the operation of the SHWSTW. 5. Inform North Lantau Refuse Transfer Station (NLTS) operator if exceedance is considered to be caused by the operation of NLTS. |
Exceedance of action level (Odour Complaints) |
1. Identify source/reason of exceedance; 2. Carry out odour patrol to determinate odour intensity. |
1. Carry out investigation and verify the complaint whether it is related to potential odour emission from the nearby SHWSTW; 2. Carry out investigation to identify the source/reason of exceedance. Investigation should be completed within 2 weeks; 3. Rectify any unacceptable practice; 4. Implement more mitigation measures if necessary; 5. Inform DSD or the operator of the SHWSTW if exceedance is considered to be caused by the operation of the SHWSTW. 6. Inform NLTS operator if exceedance is considered to be caused by the operation of NLTS. |
Limit Level |
|
|
Exceedance of limit level |
1. Identify source/reason of exceedance; 2. Inform EPD; 3. Repeat odour patrol to confirm findings; 4. Increase odour patrol frequency to bi-weekly; 5. Assess effectiveness of remedial action and keep EPD informed of the results; 6. If exceedance stops, cease additional odour patrol. |
1. Carry out investigation to identify the source/reason of exceedance. Investigation should be completed within 2 week; 2. Rectify any unacceptable practice; 3. Formulate remedial actions; 4. Ensure remedial actions properly implemented; 5. If exceedance continues, consider what more/enhanced mitigation measures should be implemented; 6. Inform DSD or the operator of the SHWSTW if exceedance is considered to be caused by the operation of the SHWSTW. |
Note: (a) Project Proponent shall identify an implementation agent. |
Environmental mitigation measures (related to air quality, water quality, waste, land contamination, hazard-to-life, and landscape and visual) to be implemented during the operation phase of the Project are recommended in the approved EIA Report and EM&A Manual and are summarised in Annex D. Monthly site audits for operation phase will be carried out to check the implementation of these measures.
Compliance audits are to be undertaken to ensure that a valid discharge licence has been issued by EPD prior to the discharge of effluent from the operation of the Project site. The audit shall be conducted to ensure that the effluent quality is in compliance with the discharge licence requirements. The effluent quality shall meet the discharge limits as described in Table 3.9.
Table 3.9 Discharge Limits for Effluent
Parameters |
Discharge Limit (mg/L) |
Flow Rate (m3/day) |
685 |
pH (pH units) |
6-10 (a) |
Suspended Solids |
800 |
Biochemical Oxygen Demand (5 days, 20°) |
800 |
Chemical Oxygen Demand |
2,000 |
Oil & Grease |
40 |
Total Nitrogen |
200 |
Total Phosphorus |
50 |
Surfactants (total) |
25 |
Note: (a) Range. |
In accordance with EM&A Manual, the landscape and visual mitigation measures shall be implemented.
For operation phase, site inspection shall be conducted once a month for the first year of operation of the Project. All measures as stated in the implementation schedule of the EM&A Manual (see Annex D), including compensatory planting, undertaken by both the Contractor and the specialist Landscape Sub-Contractor during the first year of the operation phase shall be audited by a Registered Landscape Architect (RLA) to ensure compliance with the intended aims of the measures and the effectiveness of the mitigation measures. After the one-year maintenance period, the landscape maintenance and monitoring shall be carried out by the Contractor.
Monitoring results of air quality parameters from stack emissions of the centralised air pollution control system, the ammonia stripping plant and the cogeneration units will be provided once available to show compliance with the monitoring requirements stated in the EM&A Manual (Rev. F) to support the termination of the commissioning phase EM&A programme.
The concentrations of concerned air pollutants emitted from the stacks of the CAPCS, CHP, and ASP during the reporting period are monitored on-line by the continuous environmental monitoring system (CEMS). During the reporting period, there is no need to operate the standby flare and therefore no monitoring of the flare stack was undertaken.
With reference to the emission limits shown in Tables 3.2, 3.3 and 3.4, the hourly average concentrations and the number of exceedances of the concerned air emissions monitored for the CAPCS, CHP and ASP during this reporting period are presented in Tables 4.1 to 4.5.
It should be noted that measurements recorded under abnormal operating conditions, e.g. start up and stopping of stacks, unstable operation, test runs and interference of sensor, are disregarded.
Table 4.1 Hourly Average of Parameters Recorded for CAPCS
Parameter |
Range of Hourly Average Conc. (mg/Nm3) |
Emission Limit (mg/Nm3) |
Exceedance Identified |
Remarks |
VOCs (including methane) |
0 – 0 |
680 |
Nil |
Nil |
Dust (or TSP) |
0.2 – 3.2 |
6 |
Nil |
Nil |
Odour (including NH3 & H2S) (a) |
0 – 337 |
220 |
Identified (b) |
CAPCS was under maintenance. |
Notes: (a) The odour unit is OU/Nm3. (b) Dates with exceedances on Odour (including NH3 & H2S) (number of exceedances on the day) were identified on 9 (3) and 17 (4) April 2020. |
Table 4.2 Hourly Average of Parameters Recorded for CHP 1
Parameter |
Range of Hourly Average Conc. (mg/Nm3) (a) |
Max. Emission Limit (mg/Nm3) |
Exceedance Identified |
Remarks |
Dust (or TSP) |
0 – 14 |
15 |
Nil |
Nil |
Carbon Monoxide |
0 – 448 |
650 |
Nil |
Nil |
NOx |
0 – 352 |
300 |
Identified (d) |
Supplier had been arranged to check the performance of the CHP and maintenance will be arranged after detailed investigation. |
SO2 |
0 – 42 |
50 |
Nil |
Nil |
NMVOCs (b) |
Nil |
150 |
Nil |
Nil |
VOCs (including methane) (c) |
0 – 1,809 |
1,500 |
Identified (e) |
Supplier had been arranged to check the performance of the CHP and maintenance will be arranged after detailed investigation. |
HCl |
0 – 8 |
10 |
Nil |
Nil |
HF |
0.0 – 1.0 |
1 |
Nil |
Nil |
Notes: (a) All values refer to an oxygen content in the exhaust gas of 6% and dry basis. (b) No sampling was undertaken at CHP 1 as biogas production rate could not sustain the operation of the CHP stack for the scheduled sampling on 11 February 2020. (c) The VOCs emission limit include methane as biogas is adopted as fuel in the combustion process. (d) One exceedance on NOx was identified on 15 April 2020. (e) Dates with exceedances on VOCs (including methane) (number of exceedances on the day) were identified on 14 (1) and 15 (2) April 2020. |
Table 4.3 Hourly Average of Parameters Recorded for CHP 2
Parameter |
Range of Hourly Average Conc. (mg/Nm3) (a) (b) |
Max. Emission Limit (mg/Nm3) |
Exceedance Identified |
Remarks |
Dust (or TSP) |
0 – 10 |
15 |
Nil |
Nil |
Carbon Monoxide |
0 – 97 |
650 |
Nil |
Nil |
NOx |
0 – 362 |
300 |
Identified (d) |
Supplier had been arranged to check the performance of the CHP and maintenance will be arranged after detailed investigation. |
SO2 |
0 – 48 |
50 |
Nil |
Nil |
NMVOCs (b) |
Nil |
150 |
Nil |
Nil |
VOCs (including methane) (c) |
0 – 1,407 |
1,500 |
Nil |
Nil |
HCl |
0 – 1 |
10 |
Nil |
Nil |
HF |
0 – 1.0 |
1 |
Nil |
Nil |
Notes: (a) All values refer to an oxygen content in the exhaust gas of 6% and dry basis. (b) No sampling was undertaken at CHP 2 as biogas production rate could not sustain the operation of the CHP stack for the scheduled sampling on 11 February 2020. (c) The VOCs emission limit include methane as biogas is adopted as fuel in the combustion process. (d) Dates with exceedances on NOx (number of exceedances on the day) were identified on 9 (1), 14 (3), 18 (7), 19 (1), 20 (8), 21 (21), 24 (4), 29 (7) and 30 (5) April 2020. |
Table 4.4 Hourly Average of Parameters Recorded for CHP 3
Parameter |
Range of Hourly Average Conc. (mg/Nm3) (a) |
Max. Emission Limit (mg/Nm3) |
Exceedances Identified |
Remarks |
Dust (or TSP) |
0 – 9 |
15 |
Nil |
Nil |
Carbon Monoxide |
0 – 248 |
650 |
Nil |
Nil |
NOx |
0 – 397 |
300 |
Identified (d) |
Supplier had been arranged to check the performance of the CHP and maintenance will be arranged after detailed investigation. |
SO2 |
0 – 43 |
50 |
Nil |
Nil |
NMVOCs (b) |
Nil |
150 |
Nil |
Nil |
VOCs (including methane) (c) |
0 – 1,566 |
1,500 |
Identified (e) |
Supplier had been arranged to check the performance of the CHP and maintenance will be arranged after detailed investigation. |
HCl |
0 – 3 |
10 |
Nil |
Nil |
HF |
0 – 1.0 |
1 |
Nil |
Nil |
Notes: (a) All values refer to an oxygen content in the exhaust gas of 6% and dry basis. (b) Quarterly sampling of NMVOCs was conducted in CHP3 on 11 February 2020. The hourly average concentration for NMVOCs was 3.3 mg/Nm3. No exceedance was identified. (c) The VOCs emission limit include methane as biogas is adopted as fuel in the combustion process. (d) Dates with exceedances on NOx (number of exceedances on the day) were identified on 4 (9), 5 (18), 6 (12), 7 (1), 8 (2), 9 (11), 13 (3) and 23 (1) April 2020. (e) One exceedance on VOCs (including methane) was identified on 23 April 2020. |
Table 4.5 Hourly Average of Parameters Recorded for ASP
Parameter |
Range of Hourly Average Conc. (mg/Nm3) (a) |
Max. Emission Limit (mg/Nm3) |
Exceedances Identified |
Remarks |
Dust (or TSP) |
0.0 – 2.5 |
5 |
Nil |
Nil |
Carbon Monoxide |
0 – 267 |
100 |
Identified (c) |
Modification of the ASP is being arranged with the supplier. The supplier will be on-site to complete the modification and review the ASP operation. |
NOx |
0 – 377 |
200 |
Identified (d) |
Modification of the ASP is being arranged with the supplier. The supplier will be on-site to complete the modification and review the ASP operation. |
SO2 |
0 – 27 |
50 |
Nil |
Nil |
VOCs (including methane) (b) |
0 – 65 |
20 |
Identified (e) |
Modification of the ASP is being arranged with the supplier. The supplier will be on-site to complete the modification and review the ASP operation. |
NH3 |
0 – 242 |
35 |
Identified (f) |
Modification of the ASP is being arranged with the supplier. The supplier will be on-site to complete the modification and review the ASP operation. |
HCl |
0 – 10 |
10 |
Nil |
Nil |
HF |
0 – 1.5 |
1 |
Identified (g) |
Modification of the ASP is being arranged with the supplier. The supplier will be on-site to complete the modification and review the ASP operation. |
Notes: (a) All values refer to an oxygen content in the exhaust gas of 11% and dry basis. (b) The VOCs emission limit include methane as biogas is adopted as fuel in the combustion process. (c) 1 exceedance on Carbon Monoxide (number of exceedances on the day) was identified on 2 April 2020. (d) Dates with exceedances on NOx (number of exceedances on the day) were identified on 1 (3), 2 (1), 3 (3), 4 (7), 8 (4), 9 (1) 15 (2), 16 (2), 22 (1) and 30 (1) April 2020. (e) Dates with exceedances on VOCs (including methane) (number of exceedances on the day) were identified on 2 (1), 8 (1) and 22 (1) April 2020. (f) Dates with exceedances on NH3 (number of exceedances on the day) were identified on 1 (5), 2 (17), 3 (13), 4 (7), 10 (1), 16 (3), 19 (4), 20 (2), 22 (1), 23 (5), 24 (1), 25 (1) and 26 (5) April 2020. (g) One exceedances on HF was identified on 7 April 2020. |
No odour patrol was required to be conducted for this reporting period.
Effluent discharge was sampled monthly from the Effluent Storage Tank as stipulated in the operation phase discharge licence. The results of the discharge sample is recorded in Table 4.6.
Table 4.6 Results of the Discharge Sample
Parameters |
Discharged Effluent Concentration (mg/L) |
Discharge Limit (mg/L) |
Compliance with Discharge Limit |
pH (pH units) |
7.48 – 7.88 |
6-10 (a) |
Yes |
Suspended Solids (b) |
26 |
800 |
Yes |
Biochemical Oxygen Demand (5 days, 20°) (b) |
11 |
800 |
Yes |
Chemical Oxygen Demand (b) |
360 |
2,000 |
Yes |
Oil & Grease (b) |
<5 |
40 |
Yes |
Total Nitrogen (b) |
32.7 |
200 |
Yes |
Total Phosphorus (b) |
31.9 |
50 |
Yes |
Surfactants (total) (b) |
<1.0 |
25 |
Yes |
Notes: (a) Daily Average. (b) Effluent sample collected on 8 April 2020. |
No exceedance of discharge limit was recorded during the reporting period.
Wastes generated from the operation of the Project include chemical waste, wastes generated from pre-treatment process and general refuse ([4]). Reference has been made to the Monthly Summary Waste Flow Table prepared by the Contractor (see Annex E). With reference to the relevant handling records and trip tickets of this Project, the quantities of different types of waste generated from the operation of the Project in the reporting month are summarised in Table 4.7.
Table 4.7 Quantities of Waste Generated from the Operation of the Project
Month / Year |
Chemical Waste |
Waste Generated from
|
General Refuse |
||
|
Disposal of at CWTC |
Disposed of at Landfill (a) |
Recycled (b) |
Disposed of at Landfill (a) |
Recycled (c) |
April 2020 |
0 L |
363.92 tonnes |
0.00 tonnes |
2.42 tonnes (d) |
0 kg |
Notes: (a) Waste generated from pre-treatment process and general refuse other than chemical waste and recyclables were disposed of at NENT landfill by sub-contractors. (b) Among waste generated from pre-treatment process, 0.00 kg of metals, 0.00 kg of papers/ cardboard packing and 0.00 kg of plastics were sent to recyclers for recycling during the reporting period. (c) Among general refuse, 0.00 kg of metals, 0.00 kg of papers/ cardboard packing and 0.00 kg of plastics were sent to recyclers for recycling during the reporting period. (d) It was assumed that four 240-litre bins filled with 80% of general refuse were collected at each collection. The general refuse density was assumed to be around 0.15 kg/L. |
The monthly inspection of the landscape and visual mitigation measures for the operation phase of the Project on 23 April 2020 covered the operation phase environmental site audit. Joint site inspections was conducted by representatives of the Contractor, ER, IEC and the MT on 23 April 2020 as required for the operation of the Project.
The audits checked the implementation of the recommended mitigation measures for air quality, landscape and visual, water quality, waste (land contamination) and hazard-to-life stated in the Implementation Schedule (see Annex D).
Follow-up actions resulting from the last site inspections were generally taken as reported by the Contractor.
Key observations during the reporting period are summarised as follows:
23 April 2020
· No particular observation during this inspection.
Other than the above observations, the Contractor has implemented environmental mitigation measures recommended in the approved EIA Report and EM&A Manual.
Inspection of the landscape and visual mitigation measures for the operation phase of the Project was performed on 23 April 2020.
It was confirmed that the necessary landscape and visual mitigation measures during the operation phase as summarised in Annex D were generally implemented by the Contractor. No specific observation was found during site inspections on 23 April 2020. No non-compliance in relation to the landscape and visual mitigation measures was identified during the site audits in this reporting period and therefore no further actions are required. The ET/MT will keep track of the EM&A programme to check compliance with environmental requirements and the proper implementation of all necessary mitigation measures.
Non-compliance of emission limits for CAPCS, CHP and ASP were recorded during the reporting period.
The Contractor has reviewed the organic waste treatment processes (i.e. waste reception, waste pre-treatment, anaerobic digesters, and composting processes) and found that they were operated normally during the reporting period. The Contractor has investigated air pollution control system and the combustion system of the CAPCS, CHP and ASP and identified the following potential causes for the exceedance.
(a) The CAPCS was undergoing fine-tuning for performance optimisation. As a result, it could not effectively remove odorous gases (e.g. NH3 and H2S) and caused exceedances of odour limits for the CAPCS;
(b) CHP setting was undergoing fine-tuning for performance optimisation. Therefore, it could not effectively remove NOx and VOCs (including methane) at a certain period of time which leads to the exceedance for NOx and VOCs (including methane) limit for the CHP stacks;
(c) The ongoing performance optimisation of the ASP result in the incomplete combustion of biogas. The unstable emission leads to the exceedances of Carbon Monoxide, NOx, VOCs (including methane), NH3 and HF in ASP.
For item (a) and (b), it was arranged with the supplier of CAPCS and CHPs to check the performance of the stacks onsite during the reporting period. However the supplier could not travel to Hong Kong during this reporting period due to restrictive travel arrangement during this reporting period. The supplier will conduct a detailed investigation of the remaining exceedance recorded on the CAPCS and CHPs. After the investigation, the Contractor will perform the maintenance work according to suggestions raised by the supplier in the next reporting period.
For item (c), parts of the modification works has been completed, with more components waiting to be delivered to Hong Kong. The Contractor has scheduled the remaining modification work for the next few reporting periods with schedule shutdown of the ASP to facilitate the installation of equipment for performance optimisation.
The investigation report is presented in Annex G.
· Operation of the Project.
· Modification of the ASP to control the air emission.
This EM&A Report presents the EM&A programme undertaken during the reporting period from 1 to 30 April 2020 in accordance with EM&A Manual (Version F) and requirements of EP (FEP-01/395/2010/C).
For the operation phase, exceedances of the emission limits for CAPCS, CHP and ASP stack monitoring were recorded under normal operating conditions during the reporting period (see Table 8.1).
Table 8.1 Exceedances for Stack Emissions
Stack |
Exceedances During the Reporting Period |
Centralised Air Pollution Control Unit (CAPCS) |
· Exceeded emission limit of Odour (including NH3 & H2S) on 9 and 17 April 2020 |
Cogeneration Unit (CHP) |
· Exceeded emission limit of NOx on 4, 5, 6, 7, 8, 9, 13, 14, 15, 18, 19, 20 ,21, 23, 24, 29 and 30 April 2020 · Exceeded emission limit of VOCs (including methane) on 14, 15 and 23 April 2020 |
Ammonia Stripping Plant (ASP) |
· Exceeded emission limit on Carbon Monoxide on 4 and 2 April 2020 · Exceeded emission limit of NOx on 1, 2, 3, 4, 8, 9, 15, 16, 22 and 30 April 2020 · Exceeded emission limit of VOCs (including methane) on 2, 8 and 22 April 2020 · Exceeded emission limit of NH3 on 1, 2, 3, 4, 10, 16, 19, 20, 22, 23, 24, 25 and 26 April 2020 · Exceeded emission limit of HF on 7 April 2020 |
Exceedances in emission parameters of CAPCS, CHP and ASP were found to be a result of the continuous fine-tuning of CAPCS, CHP and ASP setting.
The Contractor has implemented mitigation measures to control the exceedance, which is the modification of the CAPCS, CHP and ASP to optimise overall performance.
No non-compliance to the effluent discharge limit was recorded during this reporting period.
The environmental control /mitigation measures related to air quality, water quality, waste (including land contamination prevention), hazard-to-life and landscape and visual recommended in the approved EIA Report and the EM&A Manual were properly implemented by the Contractor during the reporting month.
Monthly landscape and visual monitoring were conducted in the reporting period. The necessary landscape and visual mitigation measures recommended in the approved EIA Report were generally implemented by the Contractor.
No complaint/summon/prosecution was received.
([1]) As some of the minor items are yet to be closed out in March 2019, the construction phase EM&A programme and Operation Phase EM&A programme were undertaking in parallel in March 2019.
([2]) A standby facility. Only operate when the CHPs are not in operation or when the biogas generated exceeded the utilisation rate of the CHPs.